We first installed the system with the inverters in the plant room. About a year later the client decided they wanted the inverters on the roof instead. A tricky job on a working system — but with our engineers, it was done.
Phase 1: our team installed the solar system, with the inverters, isolators and cabling neatly fitted in the plant room. Phase 2, a year later: the client asked for the inverters to go on the roof — so every DC cable needed a new route.
We worked from the scaffold in one week in August 2025 — on a live system. New tray across the roof, inverters fitted on frames, cables re-run and tested.
In September 2025 we connected the inverters to the internet. Everything is on, and the live monitoring screen in reception shows the system working.





Solar PV and battery installations across the UK — from roof to inverter to switch-on, by our own team.
Watch on YouTube →Moves, repairs, re-cabling or monitoring — send us the details.